Carpinteria Breaks Ground on Historic Water Purification Project to Secure Local Water Future

A group of people in hard hats participates in a groundbreaking ceremony, holding shovels and standing in front of a construction vehicle.

CARPINTERIA, CA — May 28, 2026 — The Carpinteria Valley Water District (CVWD) and Carpinteria Sanitary District (CSD) broke ground today on the Carpinteria Advanced Purification Project (CAPP), a landmark initiative designed to provide a drought-proof, locally controlled water supply for the community. 

The project will recycle over 1 million gallons of water per day, meeting approximately 25% of Carpinteria’s annual water needs. By treating wastewater with proven, advanced technology and injecting the purified water into the Carpinteria Groundwater Basin, CAPP will creates a reliable, year-round source that is resilient to drought conditions and climate change. 

"I’m excited for the opportunity to serve the Carpinteria community and construct the water purification project for improved water management in the future," Kelley Dyer, General Manager of the Carpinteria Valley Water District, said. " CAPP represents a critical step in strengthening our local water supply by helping recharge the groundwater basin. Following recent drought conditions that reduced basin levels, this project will help maintain more stable groundwater supplies during future dry periods.” 

Craig Murray, General Manager of the Carpinteria Sanitary District, highlighted the technological evolution of the partnership. "Carpinteria Sanitary District is excited and ready to enter a new era. We are becoming a resource recovery agency. Facilities like the one we are building take treated water that we currently release to the ocean and purify it for reuse. Agencies like ours can now use technology to keep water for the community.” 

The May 28 Groundbreaking Ceremony was attended by local, state and federal representatives from the State Water Resources Control Board, Department of Water Resources, United States Bureau of Reclamation, State Sen. Limon, State Rep. Gregg Hart, Carpinteria Mayor Natalia Alarcon, Santa Barbara County Supervisor Roy Lee , CVWD Board, CSD Board, and City Council who commemorated the significant project for enhancing community resilience in Carpinteria.  

Project Timeline and Construction Phasing 

Construction activities are scheduled to occur in phases through 2028 to minimize community impact: 

  • Advanced Water Purification Facility (AWPF): Construction on the facility, located within the existing CSD plant on 6th Street, is set to begin in June and continue through mid-2028. 
  • Conveyance Pipelines: Installation of approximately one mile of purified water pipelines is scheduled to begin in June  
  • Injection and Monitoring Wells: Drilling for the two injection wells and monitoring clusters is slated to begin in late 2026 and continue into 2027. 

Investing in Resilience 

CAPP represents a 50-year investment in local water security. The $90 million project is supported by over $35 million in state and federal grants, including funding from the U.S. Bureau of Reclamation, State Water Resources Control Board, and the California Department of Water Resources. The balance of funding will be met by a low interest loan from the State Water Resources Control Board. 

The advanced purification process—utilizing membrane filtration, reverse osmosis, and UV/advanced oxidation—ensures the final product exceeds all public health safety standards, providing the cleanest water source the basin has ever received. 

For more information and construction updates, please visit cvwd.net/CAPP. 